Hi PeterHolland,
Thanks very much for your reply,
Yes, you are right, I worked at a customer with the connector,
And everything was planned from the Z, simply brilliant,
But we will not have it,
And I can not plan correctly on unix / tws,
Especially when I have somewhat complicated cycles,
It the reverse of what I ask,
That's why I tell the unix team,
That with the Z, I have a Rolls Royce in my hands,
We requested the assistance of an IBM consultant,
Thank you again for spending time on my question.
Subject: scheduling between OPC and TWS give unpredictable result ?
Posted: Mon Mar 27, 2017 11:31 pm (GMT 5.5)
Hi PeterHolland,
Thanks very much for your reply,
Yes, you are right, I worked at a customer with the connector,
And everything was planned from the Z, simply brilliant,
But we will not have it,
And I can not plan correctly on unix / tws,
Especially when I have somewhat complicated cycles,
It the reverse of what I ask,
That's why I tell the unix team,
That with the Z, I have a Rolls Royce in my hands,
We requested the assistance of an IBM consultant,
Thank you again for spending time on my question.